Show last authors
1 If during a CQM Audit, a Vendor does one of the following:
2
3 * Modifies documented information after being advised of a non-conformity, and the Vendor then attempts to argue there is no non-conformity because of the modified documented information, even though the documented information was modified only after the beginning of the audit, or
4 * The Vendor intentionally hides records or claims absence of production volume during a certain time period with the apparent intention to prevent the auditor from obtaining evidence for deficiencies of conducting required controls or for poor record keeping,
5
6 then:
7
8 * Document the related observations, preferably in the field for Additional Information from the Auditor on the cqmAP "Coverpage" worksheet, and
9 * Select Rank "D" for every item included in the audit scope as defined by the Vendor in the cqmAP "Audit Scope & Compliance" worksheet, and
10 * Select "F - CQM Audit failed" for every label included in the Audit Scope in the section "Certification Recommendation" on the cqmAP "Coverpage" worksheet, and
11 * The CQM Auditor may end the audit at this stage.